web stats analysis
Foundation
 
Michael Ubaldi, August 16, 2004.
 

The forces of terror won't win:

For the third time in two weeks, Iraqi and U.S. engineers have brought more electricity to the people of Iraq by commissioning a power plant in Southern Iraq. The 52 Megawatt generator at the Khor Az Zubayr Power Plant, located 40 kilometers south of Basrah, fired for the first time today, bringing enough power on line to service 156,000 Iraqi homes.

“This is a very important step in overcoming the power shortage across the country,” said Raad Shalal, a senior Iraq Ministry of Electricity official. “This will help us reach our goal of increasing power for the country.”


Meanwhile, more evidence points to Saddam's permanent outsourcing of WMD equipment and material in early 2003.

AND: Michael Ledeen lays out the facts.